This page documents the goals and results for a series of milestones for the first implementation of RAMCloud. Each milestone last 2 weeks, ending on a Monday.

Milestone 17: ends October 4, 2010

  • Ryan goals:
    • Finish edits in response to code review.
    • File bugs on remaining important issues in FastTransport.
  • Ryan actual:
    •  
  • Steve goals:
    • Finish Infiniband Transport and Driver
    • Simple benchmarks of the above
    • Restart work on new Log and Segment code
  • Steve actual:
    •  
  • Diego goals:
    • Finish updates to Transport API.
    • Update Driver API.
    • Finish Ethernet packet driver.
  • Diego actual:
    •  

Milestone 16: ends September 21, 2010

  • Ryan goals:
    • Code review FastTransport, commit with review changes
    • Analyze performance of FastTransport.
  • Ryan actual:
    • Working through code review:
      • Done with everything except FastTransport*
      • Worked through easy comments in FastTransport.h
  • Steve goals:
    • Infiniband transport & driver
    • Continue working on performance discrepancy with Mellanox
  • Steve actual:
    • Driver mostly done (blocked on ServiceLocator), does copying right now to avoid memory registration issues
    • Transport 80% coded
    • Mellanox: our hardware is slower, but we're not sure why (they get latency up to 40% better than us)
  • Diego goals:
    • Finish ServiceLocator.
    • Finish Ethernet packet driver.
    • Resolve monitor issue.
  • Diego actual:
    • Class/code review done, but integration still in progress.
    • No packet driver work.
    • Monitor #5 works
  • John goals:
    • TCPTransport performance improvements.
    • Class prep.
  • John actual:
    • No TCPTransport work yet.

Milestone 15: ends September 7, 2010

  • Ryan goals:
    • Tuning/code review for FastTransport
  • Ryan actual:
    • Code review imminent
  • Steve goals:
    • Gone one week
    • Infiniband transport working
  • Steve actual:
    • Gone one week
    • Partial Infiniband transport (waiting for ServiceLocators)
    • Talking with Mellanox about performance
  • Diego goals:
    • Working monitor
    • Driver to send raw Ethernet packets through the kernel
  • Diego actual:
    • Monitor still broken
    • Ethernet packet driver exists but not in proper form
    • Implemented ServiceLocator class; undergoing code review, not integrating cleanly
  • John goals:
    • Really really check in Client/Server changes.
    • Start on smaller issues.
  • John actual:
    • Committed Client/Server changes
    • Fixed several smaller issues (cpplint, etc.)

Milestone 14: ends August 23, 2010

  • Ryan goals:
    • Finish documentation and tests for FastTransport (1 week)
    • Possible next steps:
      • Redo sessions
      • Add UDP layer
  • Ryan actual:
    • A few more unit tests to write for FastTransport
    • More work needed on docs
    • FastTransport currently ~1300 lines
  • Steve goals:
    • Learn about Infiniband software layers
    • Start on Infiniband Transport class
  • Steve actual:
    • Still learning Infiniband, writing simple stand-alone app
    • Setup code for Infiniband complex
    • Mellanox person coming tomorrow for training
  • Diego goals:
    • On vacation
  • Diego actual:
    • Vacation
  • John goals:
    • Finish Client/Server changes and check in (1 week)
    • Odds and ends
  • John actual:
    • Client/Server changes code-reviewed, working on followups
    • Switched to using exceptions instead of Status returns.

Milestone 13: ends August 9, 2010

  • Ryan:
    • New transport working without timers
    • Take basic performance measurements of new transport
    • Timers working with new transport
  • Ryan results:
    • C++ FastTransport implementation compiles and is showing signs of life, but has almost no tests or documentation yet.
    • It looks like the Session mechanism is going to need a redesign.
  • Steve goals:
    • Intel driver completely working in user space
    • Basic user-space 10G performance measurements (without fast transport)
    • Ideal: measure performance with user-space driver and new transport
  • Steve results:
    • Mellanox NICs and switch arrived
    • Got Infiniband and 10GE pings working using "out-of-the-box" software.
    • Starting to learn about Infiniband verbs
    • Intel work is on hold for now
  • Diego:
    • Finish translating ClientSession into C++.
    • On vacation
  • John goals:
    • Client converted to C++, upgraded for full use of Buffers, integrated with RAMCloud
  • John results:
    • Client converted to C++ and tested, along with Server.
    • Several new header files, such as Rpc.h and Table.h
    • All existing C++ code (including ClientMain and Bench) now uses the new Client.
    • Still need to convert the Python bindings and Python code.

Milestone 12: ends July 26, 2010

  • Ryan:
    • Implement a few specific benchmarks using Metrics counters (actual: no change)
    • Commit Metrics class (actual: done)
    • Aggregator classes (actual: started)
    • Additional: started translating Transport from Python to C++; coded InboundMessage; working on OutboundMessage.
  • Steve:
    • Rerun E1000 measurements on new machines (actual: done, but slightly slower than HiStar machines: 19 us for 64 bytes vs. 18.4 us)
    • 10G driver running in user space (actual: kernel pings work; using "HugeTLB" to map big pages, pin; wrote "HugeTLBPhys" driver to return physical addresses; all that's left is to map device registers into user space)
  • Diego goals:
    • Finish Python version of fast transport
    • Possibly start on logging mechanism
  • Diego results:
    • Python version done
    • Committed basic logging (prints to stderr)
    • Helping Ryan with Python->C++ translation of Transport

Milestone 11: ends July 12, 2010

  • Ryan:
    • 2 or 3 basic benchmarks (est: 3 days; actual: some simple benchmarks running, Metrics class ready for code review)
    • Integrate into Makefile (est: 1 day; actual: done, server started automatically for tests now)
  • Steve:
    • Setup machines, send RAMCloud packets to/from each machine (actual: done)
    • Experiment with 10G user-space driver (actual: works using standard in-kernel approach, not yet working from user space)
    • Rerun E1000 tests on new machines (actual: not done)
    • Log stuff (actual: not done)
  • Diego:
    • Finish buffer integration (actual: done, merged into master)
    • More transport work (actual: still working on Python prototype; feature complete)
    • Vacation July 28-Aug. 13

Milestone 10: ends June 28, 2010

  • Ryan:
    • Performance infrastructure (actual: 3 days, basic measurements working)
  • Steve:
    • Setup machines? (actual: machines just arrived)
    • Revisions to log code (actual: log code complete rewrite (mostly coded, no tests/docs), just starting on cleaner)
  • Diego:
    • Finish buffer integration (partial progress, not done: .25 day)
    • Decompose fast transport into tasks (actual: task changed, see below)
    • Start on fast transport tasks (actual: task changed, see below)
    • Revised task: full working Python prototype on UDP (actual: mostly there: 6 days)
    • Additional task: Python mock script (reduce duplication of prototypes, other improvements: .3 day)

Milestone 9: ends June 14, 2010

...