This page documents the goals and results for a series of milestones for the first implementation of RAMCloud. Each milestone last 2 weeks, ending on a Monday.
Milestone 10: ends June 28, 2010
- Ryan:
- Performance infrastructure
- Steve:
- Setup machines?
- Revisions to log code
- Diego:
- Finish buffer integration
- Decompose fast transport into tasks
- Start on fast transport tasks
Milestone 9: ends June 14, 2010
- Ryan:
- Benchmark planning (actual: worked mostly on this; some initial end-to-end measurements working)
- Try out simulator for performance analysis (actual: tried it, but not sure how interesting it is yet)
- Steve:
- 6 machines ordered (est: 1 day; actual: in purchasing)
- Set machines up (est: 1 day; actual: N/A)
- Cleanup log code (TBDactual: just getting started)
- Understand existing drivers (w. Aravind) (actual: done)
- Aravind:
- Transfer knowledge
- Diego:
- Replicate Aravind 11 usec numbers (est: 1 day) (actual: done)
- Take over fast transport from Aravind (to be fleshed out ASAPactual: done)
- Integrate Buffer into code base (actual: partial progress, 1 day)
Milestone 8: ends May 31, 2010
...