This page documents the goals and results for a series of milestones for the first implementation of RAMCloud. Each milestone last 2 weeks, ending on a Monday.

Milestone 10: ends June 28, 2010

  • Ryan:
    • Performance infrastructure
  • Steve:
    • Setup machines?
    • Revisions to log code
  • Diego:
    • Finish buffer integration
    • Decompose fast transport into tasks
    • Start on fast transport tasks

Milestone 9: ends June 14, 2010

  • Ryan:
    • Benchmark planning (actual: worked mostly on this; some initial end-to-end measurements working)
    • Try out simulator for performance analysis (actual: tried it, but not sure how interesting it is yet)
  • Steve:
    • 6 machines ordered (est: 1 day; actual: in purchasing)
    • Set machines up (est: 1 day; actual: N/A)
    • Cleanup log code (TBDactual: just getting started)
    • Understand existing drivers (w. Aravind) (actual: done)
  • Aravind:
    • Transfer knowledge
  • Diego:
    • Replicate Aravind 11 usec numbers (est: 1 day) (actual: done)
    • Take over fast transport from Aravind (to be fleshed out ASAPactual: done)
    • Integrate Buffer into code base (actual: partial progress, 1 day)

Milestone 8: ends May 31, 2010

...