- Ryan:
- Performance infrastructure (actual: 3 days, basic measurements working)
- Steve:
- Setup machines? (actual: machines just arrived)
- Revisions to log code (actual: log code complete rewrite (mostly coded, no tests/docs), just starting on cleaner)
- Diego:
- Finish buffer integration (partial progress, not done: .25 day)
- Decompose fast transport into tasks (actual: task changed, see below)
- Start on fast transport tasks (actual: task changed, see below)
- Revised task: full working Python prototype on UDP (actual: mostly there: 6 days)
- Additional task: Python mock script (reduce duplication of prototypes, other improvements: .3 day)
Milestone 9: ends June 14, 2010
...