- Ryan:
- Working on other projects/quals
- Steve:
- Working on other projects/quals
- Aravind:
- Finish testing/docs for RPC driver (est: 2 days; actual: 2 days, done)
- Write RPC transport class (est: 5 days; actual: 1 day, not done)
- GSRC talk (est: 0; actual: 2 days, done)
- POMI poster (est: 0; actual 0.5 day)
- Diego:
- Buffer chunk deallocation (est: 2 days; actual: 2.25 days, done)
- Finish TCPTransport cleanup (est: 1 day; actual: .625 days, done)
- Try out Google Mock framework (est: 1 day; actual: .875 days, done/discarded)
Milestone 7: ends May 17, 2010
...