This page documents the goals and results for a series of milestones for the first implementation of RAMCloud. Each milestone last 2 weeks, ending on a Monday.

Milestone 9: ends June 14, 2010

  • Ryan:
    • Benchmark planning
  • Steve:
    • 6 machines ordered (est: 1 day)
    • Set machines up (est: 1 day)
    • Cleanup log code (TBD)
  • Aravind:
  • Diego:
    • Replicate Aravind 11 usec numbers (est: 1 day)
    • Take over fast transport from Aravind (to be fleshed out ASAP)

Milestone 8: ends May 31, 2010

  • Ryan:
    • Working on other projects/quals
  • Steve:
    • Working on other projects/quals
  • Aravind:
    • Finish testing/docs for RPC driver (est: 2 days; actual: 2 days, done)
    • Write RPC transport class (est: 5 days; actual: 1 day, not done)
    • GSRC talk (est: 0; actual: 2 days, done)
    • POMI poster (est: 0; actual 0.5 day)
  • Diego:
    • Buffer chunk deallocation (est: 2 days; actual: 2.25 days, done)
    • Finish TCPTransport cleanup (est: 1 day; actual: .625 days, done)
    • Try out Google Mock framework (est: 1 day; actual: .875 days, done/discarded)

...