This page documents the goals and results for a series of milestones for the first implementation of RAMCloud. Each milestone last 2 weeks, ending on a Monday.
Milestone 6: ends May 3, 2010
- Ryan:
- ...
- Steve:
- ...
- Aravind:
- ...
- Diego:
- Poster (est: 3 days)
- Unit tests and docs for TCP transport (est: 2 days)
- ZooKeeper measurements: latency/bandwidth of get/set (est: 1 day)
Milestone 5: ends April 19, 2010
- Ryan:
- Mostly working on other projects
- Flesh out design of index recovery with partitions (est: 1 day)
- Steve:
- Working on other projects
- Aravind:
- Full task list for TCP-based RPC (est: 1 day)
- Other RPC tasks TBD
- Resolve ProtocolBuffer performance disconnect (est: 1 day)
- Diego:
- TCP transport for RPC (est: 3 days) (actual: not done, 2.5 days)
- Get ZooKeeper installed and running (est: 1 day) (actual: done, 0.5 day)
- ZooKeeper measurements: latency/bandwidth of get/set (est: 1 day) (actual: not started)
...