This page documents the goals and results for a series of milestones for the first implementation of RAMCloud. Each milestone last 2 weeks, ending on a Monday.

Milestone 16: ends September 21, 2010

  • Ryan goals:
    **
  • Ryan actual:
    **
  • Steve goals:
  • Steve actual:
    **
  • Diego goals:
  • Diego actual:
    **
  • John goals:
  • John actual:

Milestone 15: ends September 7, 2010

  • Ryan goals:
    • Tuning/code review for FastTransport
  • Ryan actual:
    **
  • Steve goals:
    • Gone one week
    • Infiniband transport working
  • Steve actual:
    **
  • Diego goals:
    • Working monitor
    • Driver to send raw Ethernet packets through the kernel
  • Diego actual:
    **
  • John goals:
    • Really really check in Client/Server changes.
    • Start on smaller issues.
  • John actual:
    • Committed Client/Server changes
    • Fixed several smaller issuers (cpplint, etc.)

Milestone 14: ends August 23, 2010

...